Main Contract Package-2 (Electro-Mechanical Works)
The progress for MP-2 works (E & M works) stands completed at 99.61% as of December 31, 2023. This includes the completion of 100% of Engineering, 100% of Manufacturing & Transportation and 97.87% of Erection, Commissioning and Testing works.
Key Dates fulfilled for MP-2 Package as of January 20, 2024:
SN |
Key Milestone Description |
Date Achieved on: |
1 |
Submission of data and general drawings of all relevant electrical and mechanical equipment, showing all relevant dimensions for the purpose of proper definition of all the tunnel and cavern excavation contours, KD (MP-2)-2 |
Completed on May 18, 2021 |
2 |
Submission of Basic Design for Structural Design of civil including earthing and embedment details, KD (MP-2)-2 |
Completed on January 14, 2017 |
3 |
Erection, Testing & Commissioning of Power House EOT crane, KD (MP-2)-3 |
Completed on February 01, 2020 in Service Bay |
4 |
Erection of Distributor, Pressure Testing of Distributor Unit 1, KD (MP-2)-4 |
Completed on May 23, 2020 |
5 |
Erection of Distributor, Pressure Testing of Distributor Unit 2, KD (MP-2)-8 |
Completed on February 29, 2020 |
6 |
Lowering of Stator for Unit-1, KD (MP-2)-5 |
Completed on August 11, 2021 |
7 |
Lowering of Stator for Unit-2, KD (MP-2)-9 |
Completed on August 07, 2021 |
8 |
Lowering of Rotor for Unit-1, KD (MP-2)-6 |
Completed on December 31, 2021 |
9 |
Lowering of Rotor for Unit-2, KD (MP-2)-10 |
Completed on March 09, 2022 |
10 |
Erection, Testing & Commissioning of Isolated Phase Bus Duct, KD(MP-2)-12 |
Completed on December 25, 2022. |
11 |
Erection, Testing & Commissioning of Generator Transformer, KD(MP-2)-13 |
Completed on December 26, 2022 |
12 |
Erection, Testing & Commissioning of 132 kV Gas Insulated Switchgear, KD (MP-2)-14. |
Completed on December 12, 2022. |
13 |
Boxing Up of Unit-1, KD(MP-2)-7 |
100% of works stands completed as on September 30, 2023. |
14 |
Boxing Up of Unit-2, KD(MP-2)-11 |
100% of works stands completed as on September 30, 2023. |
15 |
Completion of EHV Cable Erection and Testing, KD(MP-2)-15 |
100% completed as on May 24, 2023. |
16 |
Erection, Testing & Commissioning of Penstock Valve, KD(MP-2)-16 |
100% of the works stands completed as on September 15, 2023. |
17 |
Completion of Electro mechanical works in Pothead yard including stringing with associated transmission line tower, KD(MP-2)-17 |
100% of the works stands completed. Stringing last span of conductor from dead end tower towards the terminating structure in Nikachhu Pothead Yard completed on June 25, 2023 by BPC. |
18 |
Completion of Erection, Commissioning and Testing of Control System, KD(MP-2)-18 |
100% of the works stands completed as on October 15, 2023. |
19 |
Wet commissioning Unit-1, KD (MP-2)-19 |
To be commissioned on January 26, 2024 |
20 |
Wet commissioning Unit-2, KD (MP-2)-20 |
January 15, 2024 |