The progress for MP-2 works (E & M works) stands completed at 94.88% as of April 30, 2023. This includes the completion of 100% of Engineering, 99.93% of Manufacturing & Transportation and 72.55% of Erection, Commissioning and Testing works.

Key Dates fulfilled for MP-2 Package as of March 31, 2023:

SN

Key Milestone Description

Date Achieved on:

1

Submission of data and general drawings of all relevant electrical and mechanical equipment, showing all relevant dimensions for the purpose of proper definition of all the tunnel and cavern excavation contours, KD (MP-2)-2

  • Completed on May 18, 2021

2

Submission of Basic Design for Structural Design of civil including earthing and embedment details, KD (MP-2)-2

  • Completed on January 14, 2017

3

Erection, Testing & Commissioning of Power House  EOT crane, KD (MP-2)-3

  • Completed on February 01, 2020 in Service Bay

4

Erection of Distributor, Pressure Testing of Distributor Unit 1, KD (MP-2)-4

  • Completed on May 23, 2020

5

Erection of Distributor, Pressure Testing of Distributor Unit 2, KD (MP-2)-8

  • Completed on February 29, 2020

6

Lowering of Stator for Unit-1,  KD (MP-2)-5

  • Completed on August 11, 2021

7

Lowering of Stator for Unit-2,  KD (MP-2)-9

  • Completed on August 07, 2021

8

Lowering of Rotor for Unit-1, KD (MP-2)-6

  • Completed on December 31, 2021

9

Lowering of Rotor for Unit-2, KD (MP-2)-10

  • Completed on March 09, 2022

10

Erection, Testing & Commissioning of Isolated Phase Bus Duct, KD(MP-2)-12

  • Completed on December 25, 2022.

11

Erection, Testing & Commissioning of Generator Transformer, KD(MP-2)-13

  • Completed on December 26, 2022

12

Erection, Testing & Commissioning of 132 kV Gas Insulated Switchgear, KD (MP-2)-14.

  • Completed on December 12, 2022.

13

Boxing Up of Unit-1, KD(MP-2)-7

  • 97% of works stands completed as on March 25, 2023

14

Boxing Up of Unit-1, KD(MP-2)-11

  • 95% of works stands completed as on March 25, 2023

15

Erection, Testing & Commissioning of Penstock Valve, KD(MP-2)-16

  • 60% of the works stands completed as on March 25, 2023. False ceiling installation works completed on March 07, 2023. E&M has commenced installation activities.

16

Completion of Electro mechanical works in Pothead yard including stringing with associated  transmission line tower, KD(MP-2)-17

  • 50% of the works stands completed as on October 24, 2022. Slope Protection of Pothead Yard on-going by Geo-vertical.

 

Turbine HPU Piping works in full swing for Unit 1 and Unit 2

Turbine HPU Piping works in full swing for Unit 1 and Unit 2

Air Handing Unit AGUs installed in various floor including HVAC ducting

Air Handing Unit AGUs installed in various floor including HVAC ducting

132KV XLPE cable installation works on going for Feeder 2 in CVT

132KV XLPE cable installation works on going for Feeder 2 in CVT

Main Inlet Valves of Unit 1 and Unit 2

Main Inlet Valves of Unit 1 and Unit 2

Boxing up of Unit 1 and Unit 2 in advanced stage

Boxing up of Unit 1 and Unit 2 in advanced stage

Turbine HPU Piping works in full swing for Unit 1 and Unit 2 Air Handing Unit AGUs installed in various floor including HVAC ducting 132KV XLPE cable installation works on going for Feeder 2 in CVT Main Inlet Valves of Unit 1 and Unit 2 Boxing up of Unit 1 and Unit 2 in advanced stage