The progress for MP-2 works (E & M works) stands completed at 87.93% as of June 30, 2022. This includes the completion of 100% of Engineering, 99.85% of Manufacturing & Transportation and 35.26% of Erection, Commissioning and Testing works.
Key Dates fulfilled for MP-2 Package as of June 30, 2022:
SN |
Key Milestone Description |
Date Achieved on: |
1 |
Submission of data and general drawings of all relevant electrical and mechanical equipment, showing all relevant dimensions for the purpose of proper definition of all the tunnel and cavern excavation contours, KD (MP-2)-2 |
Completed on May 18, 2021 |
2 |
Submission of Basic Design for Structural Design of civil including earthing and embedment details, KD (MP-2)-2 |
Completed on January 14, 2017 |
3 |
Erection, Testing & Commissioning of Power House EOT crane, KD-(MP-2)-3 |
Completed on February 01, 2020 in Service Bay |
4 |
Erection of Distributor, Pressure Testing of Distributor Unit 1, KD-(MP-2)-4 |
Completed on May 23, 2020 |
5 |
Erection of Distributor, Pressure Testing of Distributor Unit 2, KD-(MP-2)-8 |
Completed on February 29, 2020 |
6 |
Lowering of Stator for Unit-1, KD(MP-2)-5 |
Completed on August 11, 2021 |
7 |
Lowering of Stator for Unit-2, KD(MP-2)-9 |
Completed on August 07, 2021 |
8 9 |
Lowering of Rotor for Unit-1 KD(MP-2)6 Lowering of Rotor for Unit-2 KD(MP-2)-10 |
Completed on December 31, 2021 Completed on March 09, 2022 |
Hence, 9 nos. Key Dates out of 20 nos. Key Dates stands achieved till date.