The progress for MP-2 works (E & M works) stands completed at 87.93% as of June 30, 2022. This includes the completion of 100% of Engineering, 99.85% of Manufacturing & Transportation and 35.26% of Erection, Commissioning and Testing works.

Key Dates fulfilled for MP-2 Package as of June 30, 2022:

SN

Key Milestone Description

Date Achieved on:

1

Submission of data and general drawings of all relevant electrical and mechanical equipment, showing all relevant dimensions for the purpose of proper definition of all the tunnel and cavern excavation contours, KD (MP-2)-2

Completed on May 18, 2021

2

Submission of Basic Design for Structural Design of civil including earthing and embedment details, KD (MP-2)-2

Completed on January 14, 2017

3

Erection, Testing & Commissioning of Power House  EOT crane, KD-(MP-2)-3

Completed on February 01, 2020 in Service Bay

4

Erection of Distributor, Pressure Testing of Distributor Unit 1, KD-(MP-2)-4

Completed on May 23, 2020

5

Erection of Distributor, Pressure Testing of Distributor Unit 2, KD-(MP-2)-8

Completed on February 29, 2020

6

Lowering of Stator for Unit-1,  KD(MP-2)-5

Completed on August 11, 2021

7

Lowering of Stator for Unit-2,  KD(MP-2)-9

Completed on August 07, 2021

8

9

Lowering of Rotor for Unit-1 KD(MP-2)6

Lowering of Rotor for Unit-2 KD(MP-2)-10

Completed on December 31, 2021

Completed on March 09, 2022 

Hence, 9 nos. Key Dates out of 20 nos. Key Dates stands achieved till date.

 

Cooling water piping works on TG

Cooling water piping works on TG

Plates and Bolts of butterfly valve stands completed

Plates and Bolts of butterfly valve stands completed

Plates and Bolts of butterfly valve stands

Plates and Bolts of butterfly valve stands

Main inlet valve OPU and Accumulator of unit 1

Main inlet valve OPU and Accumulator of unit 1

Rotor Pole

Rotor Pole

Rotor Lowering of UNIT 1

Rotor Lowering of UNIT 1

Main inlet valve OPU and Accumulator of unit 1 placed in position MIV floor

Main inlet valve OPU and Accumulator of unit 1 placed in position MIV floor

Rotor Lowering of UNIT 1 on Dec 31

Rotor Lowering of UNIT 1 on Dec 31

Cooling water piping works on TG Plates and Bolts of butterfly valve stands completed Plates and Bolts of butterfly valve stands Main inlet valve OPU and Accumulator of unit 1 Rotor Pole Rotor Lowering of UNIT 1 Main inlet valve OPU and Accumulator of unit 1 placed in position MIV floor Rotor Lowering of UNIT 1 on Dec 31