As on December 31, 2023, the progress of Power House Complex (Surge Shaft, Butterfly Valve Chamber, Pressure Shaft, Power House, Transformer Hall, and Tail Race Tunnel) is at 98.95%.

Power House Complex
Work fronts   Progress as of December 31, 2023
Surge Shaft and BVC  
  • Surge Shaft and BVC stands completed
      
Pressure Shaft
  • Erection of Pressure Shaft Steel Liner stands completed and filling of Pressure Shaft stands completed.
Power House 
  • Completed.
Control Block
  • Finishing works in progress.
Transformer Cavern
  • Completed
TRT and Gate Shaft Concreting
  • Completed
   
   
Cable Cum Ventilation Tunnel CVT

Cable Cum Ventilation Tunnel CVT

GIS Floor

GIS Floor

Surge Shaft Up view

Surge Shaft Up view

Machine hall and Control Block

Machine hall and Control Block

Surge Shaft down view

Surge Shaft down view

Transformer Hall

Transformer Hall

Cable Cum Ventilation Tunnel CVT GIS Floor Surge Shaft Up view Machine hall and Control Block Surge Shaft down view Transformer Hall