Main Contract Package-2 (Electro-Mechanical Works)
100% of the work stands completed.
Declaration of Commercial Operation Date (COD) for Unit 2 – January 25, 2024
Declaration of Commercial Operation Date (COD) for Unit 1 – February 8, 2024
Right of Way (RoW) clering & Stringing of last span of conductor from Deas End to Tower to Termininating Structure in Pothead Completed by BPC on June 25, 2023
Completed installation of all Pothead yard equipment including stringing of conductor on Gantry structure
HVAC Dusting works in comnnecting tunnel and MAT tunnel from Service Bay.
Termination of 145KV GIS completed at both GIS end and Pothead yard cale Terination end side
Filling up Nitrogen completed inall the Turbine HPU Accumulator and also MIV Accumulator. Nitrogen filled upto 100 bars.
HVAC Duct installation GIS Hall and CVT Tunnel
Testing and commissioning of Numerical relays and electro mechnical relays for Protection Panel by GE Enginners. Commenced on June 23, 2023.
Commissioning of Turbine HPU along with HPU Pipeline and Fittings