The First Aid training in coordination with Dzongkhag Health Office was conducted on November 08,2016 at THyE Transit Camp Office.

first aid training    DSC 0505


 

The Contract Agreement for Main Contract Package , MP-1(Civil & Hydro-Mechanical Works)
of 118 MW Nikachhu Hydropower Project ,was signed on April 20, 2016 with M/s Hindustan Construction Company Limited,India.

MP-1 signing2

 


 

The Contract Agreement for Main Contract Package , MP-2(Electro-Mechanical Works) of 118 MW Nikachhu Hydropower Project ,was signed on December 30, 2015 with M/s Voith Hydro Private Limited,India.

Signing of Contract Agreement for Main Contract Package

 


 

The Letter of Understanding(LoU) between THyE and Gross National Happiness Secretariat on Fisheries Development Study and Monitoring Program in Nikachhu,Trongsa was signed on December 24,2015.

Signing of LoU with GNHC and  DoL NCLRF

 


 

The total Project Cost for the 118 MW Nikachhu Hydropower Project is expected to be Nu. 11,890.800 Million to be financed with Debt: Equity ratio of 65:35.

Out of the total Equity requirement of Nu. 4,161.780 Million, ADB is funding USD 50.50 Million i.e. approximately Nu. 3,030.000 Million to RGoB (via grant of USD 25.25 Million and loan of USD 25.25 Million) to be used as equity contribution for the Project by DGPC. The remaining Nu. 1,131.00 Million will be funded by DGPC.

The debt requirement for the Project is Nu 7,729.020 Million, out of which Nu. 4,200.000 Million is met from ADB loan of USD 70.00 Million and the remaining Nu. 3,530.000 Million will be met through loan from Indian Commercial Banks (ICB).

On November 01, 2015, the financing agreements for loan of INR 3,530 Million was signed between different stakeholders at the Le Meridian Hotel in the presence of Honorable Chairman, DHI & DGPC; Managing Director, DGPC; CEO, Bank of Bhutan Limited; representatives from ADB, SBI, SBICAPS, SBICAPS Trustee Company Limited, EXIM Bank, ILS-Link Legal, THyE and other distinguished guests.

Finance agreement signing

 


 

The land lease agreement for 118 MW Nikachhu Hydropower Project was signed with the Royal Goverment of Bhutan on May 1st ,2015.


 

The 1st Annual General Meeting of Tangsibji Hydro Energy Limited( THyE) was held on May 6,2015.