Status of Construction of Project

            1. River Diversion.

            2. U/s Coffer Dam.

            3. ADIT l, ll, & lll.

 

And presently, excavation works of left & right bank, ADIT to Desilting Chamber, ADIT to D/s Gate of Chamber and ADIT to U/s Gate of Chamber are on-going at Dam site. For HRT, excavation works at ADIT IV, V, Face 3, 4, 5 & 6, are in progress. While in Power House, works at BVC, IPS, ADIT to Surge Shaft Top, ADIT to Tail Race Tunnel, ADIT to Transformer Cavern, MAT and CVT excavation are under progress.

 

2. MAIN CONTRACT PACKAGE, MP-2 (Electro-Mechnical Works).

The Contract Agreement between THyE and VOLTH for Main Contract Package, MP-2 (Electro-Mechanical Works) was signed in December, 2015. The details design, engineering and manufacturing of Electro-Mechanical equipment is on-going. The 150/30/5 T Power House EOT Crane and Earthing Rods had been received at intermediate store in P/ling. The installation of E&M equipments at site is expected to commence in beginning of 2019.

 

3.TRANSMISSION LINES (CONSTRUCTION OF 18.6 KM, 132 KV DOUBLE CIRCUIT LINE FROM NIKACHU POTHEAD YARD TO MANGDECHU POTHEAD YARD).

The construction of transmission lines has been awarded to BPC on July 14, 2014 for an amount of NU. 233 Million. BPC have sub-contracted the election works of transmission line to CDCL IN July, 2017.

CDCL had completed foundation casting of 9 tower locations and benching of 17 tower locations stands completed as of April, 2018.