One of the generating units i.e. Unit 2 of Nikachhu Hydropower Project was synchronized to the national electricity grid on January 18, 2024 marking a significant milestone for the project.
In a momentous event on November 13, 2023, the Nikachhu Hydropower Project achieved a significant milestone as the initial Dam Impoundment process commenced, marking a pivotal step forward for this ambitious endeavor.
The ceremony drew a distinguished gathering of key stakeholders, including Government Officials, Board Directors, Technical Members, Dzongkhag Officials, Local Government representatives, Contractors and dedicated THyE staff. The atmosphere was one of celebration and achievement as the project moved one step closer to completion.
The event for Dry Commissioning Ceremony of Unit 1 and Unit 2 at Power House was graced by THyE ICEO, VOITH, HCC and along with officials of THyE on October 19, 2023.
The event for lowering of Diversion Tunnel Gate and diversion of Nikachhu river from the Dam was graced by Dasho Karma Y. Raydi, Chairman-DHI, Dasho Chhewang Rinzin, Managing Director-DGPC, Dasho Dzongdag-Trongsa Dzongkhag Administration, CEO-DHyE, Director, CAD – DGPC, Superintendent of Police – Trongsa Dzongkhag, Tangsibji Gewog Administration and officials from THyE, MHP, CDCL, DHyE and HCC on March 19, 2023.